PT Triguna Internusa Pratama (TIP) is always committed to provide investment for infrastructure activities in the energy sector, including renewable energy.

img

Cilegon, Banten

In 2009, TIP expanded its business by providing gas compressor services with an installed capacity of 51 MMSCFD to serve 3x15 MMSCFD contracts located at PLTGU Cilegon, Banten. The gas produced is used for the Gas and Steam Power Plant (PLTGU) which is then supplied to the Java-Bali electricity system via a 150 kV transmission network.
In 2021 TIP obtain an additional contract for 1 unit of gas compressor with an operation capacity of 15 MMSCFD to support the gas compressor system that already exists at PLTGU Cilegon so that the configuration of service operation capacity becomes 4x15 MMSCFD.
Details :
Facilities : 3 + 1 Unit Gas Compressor
Installed Capacity : 51 + 18 MMSCFD
Pipe Location : PLTGU Cilegon, Banten
Gas Pressure : 135 - 630 psi




Sengkang, Sulawesi Selatan

In 2024, TIP provided a Rental Booster Compression Plant to support the development of the Kampung Baru Field – Sengkang Block, South Sulawesi, owned by Energy Equity Epic (Sengkang) Pty. Ltd. (E3S). The project is implemented under a Build, Operate, and Own (BOO) scheme, covering Engineering, Procurement, Construction, and Commissioning (EPCC) as well as Operation and Maintenance(O&M), with the objective of increasing gas pressure and maintaining the continuity of gas production flow.
The Booster Compression Plant facility is designed with an installed capacity of 66 MMSCFD and is integrated with existing infrastructure in the Kampung Baru area to ensure system reliability. The construction and installation phase is planned to take 12 months, with a Commercial Operation Date (COD) in Q4 2025, followed by a 64-month rental operation period, providing an efficient solution without requiring significant CAPEX investment from the field owner.
Details :
Facilities: 5 + 1 Gas Compressor Units
Installed Capacity: 66 MMSCFD
Location: Sengkang, South Sulawesi
Gas Pressure: 50–300 psig

img



img

Gresik, Jawa Timur

TIP is committed to proceed on focusing building national natural gas infrastructure, this is evinced by the start of the BOT contract scheme with PT Petrogas Jatim Utama for the construction and operation of a natural gas pipeline in 2014 in Gresik, East Java. The natural gas distribution pipeline project was used to distribute natural gas to its current customer, namely PT PJB UP Gresik.
Details : Pipe Diameter : 16 inches
Pipe Length : 20 Km
Pipe Location : Gresik, East Java
Maximum Capacity : 100 MMSCFD




Onshore Early Works EPC – Ubadari, Tangguh Block

Our company plays an active role in the implementation of the Onshore Early Works EPC Ubadari Project, located in Bintuni Bay, West Papua, as part of the development of BP Berau Ltd.’s Tangguh LNG Project. This strategic project serves as a crucial early foundation to support the main construction phase of an international‑scale oil and gas facility.
The scope of work covers Engineering, Procurement, Construction, and Commissioning (EPCC) for a range of supporting facilities, including:
• Construction Camp development with a capacity of approximately 3,500 personnel, complete with accommodation facilities, utilities, and supporting buildings.
• Electrical and power generation works, including diesel generators, MV/LV systems, substations, grounding, and lightning protection.
• Camp telecommunication systems, encompassing data networks, radio communications, GSM, TV systems, and supporting IT infrastructure.
• Integrated waste management facilities, including an incinerator, food composter, dewatering system, and supporting landfill.
• Early works infrastructure, such as access roads, laydown areas, earthworks, drainage systems, and modifications to the existing jetty.
The execution of this project demands high standards of safety, quality, and reliability, considering the remote location and the complexity of the work. Through integrated planning, cross‑disciplinary collaboration, and a robust project management approach, we are committed to delivering solutions that are safe, efficient, and sustainable, while supporting the successful implementation of a nationally strategic project in the energy sector.
The Onshore Early Works EPC Ubadari Project stands as clear evidence of our company’s capability in handling large‑scale EPC projects in the oil and gas industry, particularly during the critical early stages of development.

img



img

Tegal Gede, Bekasi

TIP started its first pipeline investment project in 2005 at Tambun-Tegal Gede in Bekasi, West Java. The pipeline, which spans 35 kilometers in length, is an important and strategic step for TIP, because the presence of this gas transmission pipeline is considered to be a solution for sustainable gas energy supply to support industrial competitiveness in Java Island.
Details :
Pipe Diameter : 8 inches
Pipe Length : 35 Km
Pipe Location : Tegal Gede, Bekasi, West Java
Maximum Capacity : 18 MMSCFD (2005)